Gloucester – Biz Space - Unit 42 / 42a (Former England Glory Match factory)

Location :
Gloucester
Client :
Bizpsace
Project Type :
Industrial / Diplapidation
Completion Year:
2025
Duration
10 Weeks
Project Overview

The client required the complete strip-out of a redundant snooker hall, church, gym, and former factory area located on the upper floor of a factory unit – once home to England Glory matches. The aim was to clear and modernise the space to improve functionality and unlock greater revenue potential.
Scope of Works
SV Contracts successfully delivered the project over a 10-week period, completing the following:
Full strip-out and disposal of all existing fixtures, fittings, bars, furniture, and loose items
Demolition and removal of all partition and blockwork walls
Removal of suspended ceilings throughout the upper floor areas
Disconnection and removal of redundant mechanical and electrical systems, including lighting, power, and industrial heating units, with all areas made good upon completion
Project Outcome

The works were completed on time and to a high standard, leaving the client with a clear, adaptable space ready for future redevelopment. The transformation has enabled the client to maximise the use of their premises and improve potential revenue streams.
For more information on how SV Contracts can support your next project, get in touch with our team today.